कालीगण्डकी करिडोरको २२० केभी प्रसारण लाइन बाढीपछि पुनःस्थापित

कालीगण्डकी क्षेत्रमा आएको बाढी र कटानका कारण क्षति पुगेको कालीगण्डकी करिडोरको २२० केभी क्षमताको दाना–खुर्कोट प्रसारण लाइन पुनःस्थापित भएको छ। म्याग्दीको अन्नपूर्ण गाउँपालिका–१ दोवा र ६ धिरचुङमा तीनवटा प्रसारण लाइनका टावर नष्ट भएका थिए। विपद्का बेला आपत्कालीन विद्युत् आपूर्ति सम्भव बनाउन क्यानडेली प्रविधि प्रयोग गरी अस्थायी टावर निर्माण गरिएको छ।

TopicsMyagdi
4 publishers · 6 headlines · developing over 7 hours
Broke firstRatopati (English) logoRatopati (English)

Kaligandaki Corridor Transmission Line Repaired After Flood Damage

Myagdi. The 220 KV Kaligandaki Corridor transmission line between Dana-Khurkot, which was damaged due to the flood and erosion of...

story6 publishers
Coverage

5 more headlines since

first · 18 Octlatest · 18 Oct
  1. Dana-Rahughat section of Kaligandaki Corridor transmission line operational

    The Nepal Electricity Authority brought the section into temporary operation by using an emergency restoration system (ESR) tower and energizing one circuit of the transmission line on Saturday night.

    myRepublica logomyRepublicaPrivatenews6 publishers
  2. Dana-Rahughat section of Kaligandaki corridor transmission line in operation

    Dana-Rahughat section, Myagdi, of 220-kV Kaligandaki Corridor transmission line damaged due to landslide and encroachment of Kaligandaki river has come into operation after 21 days.The Nepal Electricity Authority brought the section into operation in a temporary manner by using an emergency restoration system (ESR) tower by charging one circuit of the transmission line from Saturday night.The flood damaged four towers of the transmission line at Annapurna rural municipality of Myagdi district.&n

  3. Dana-Rahughat section of Kaligandaki corridor transmission line in operation

    KATHMANDU: Dana-Rahughat section, Myagdi, of 220-kV Kaligandaki Corridor transmission line damaged due to landslide and encroachment of Kaligandaki river has come into operation after 21 days. The Nepal Electricity Authority brought the section into operation in a temporary manner by using emergency restoration system (ESR) tower by charging one circuit of the transmission line from […]

  4. Temporary power transmission tower installed

    The Dana-Khurkot transmission line, part of the Kaligandaki Corridor with a capacity of 220 KV, which sustained damage due to flooding and erosion in the Kaligandaki region, has been successfully restored. A temporary tower constructed utilizing Canadian technology has been established to enable emergency electrical supply during catastrophic events. Following the destruction of three transmission line towers in Annapurna Rural Municipality-1 Dowa and 6 Dhirchang of Myagdi, 176 megawat

  5. Kaligandaki Flood: Temporary power transmission tower installed

    MYAGDI: The Dana-Khurkot transmission line, part of the Kaligandaki Corridor with a capacity of 220 KV, which sustained damage due to flooding and erosion in the Kaligandaki region, has been successfully restored. A temporary tower constructed utilizing Canadian technology has been established to enable emergency electrical supply during catastrophic events. Following the destruction of three […]