सिक्टा सिँचाइ आयोजना ५१ प्रतिशत सम्पन्न, लाभग्राही किसानको तथ्याङ्क सङ्कलन सुरु

बाँकेमा निर्माणाधीन राष्ट्रिय गौरवको सिक्टा सिँचाइ आयोजनाले ५१ प्रतिशत भौतिक प्रगति हासिल गर्दै आयोजना क्षेत्रका लाभग्राही किसानको तथ्याङ्क सङ्कलन सुरु गरेको छ। आयोजना निर्देशक राजु आचार्यका अनुसार पूर्वी र पश्चिमी मूल नहरका शाखा तथा उपशाखामार्फत हाल सिँचाइ सुविधा लिइरहेका किसानको सूची तयार गरिँदै छ। यो तथ्याङ्क सङ्कलनले पानीको वितरण तथा व्यवस्थापन प्रभावकारी बनाई सेवा लक्षित वर्गसम्म पुर्‍याउने उद्देश्य राखेको छ।

TopicsBanke
4 publishers · 5 headlines · developing over 3 hours
Broke firstNepal News (English) logoNepal News (English)

Sikta Irrigation Project reports 51 percent progress, data collections of beneficiaries underway

BANKE: The under-construction Sikta Irrigation, a national pride project, has started collecting farmers’ (water users’) data to facilitate water management to target groups. According to project director Raju Acharya, they were preparing a list of farmers who presently access the irrigation facilities under the Project system in the east and west belts. The list also […]

business5 publishers
Coverage

4 more headlines since

first · 3d agolatest · 3d ago
  1. National pride irrigation projects extend water supply to new farmland

    KATHMANDU: National pride irrigation projects have begun expanding irrigation services to additional farmland, with the Sikta Irrigation Project in Banke adding 100 hectares and the Babai Irrigation Project in Bardiya adding 50 hectares, according to the Department of Water Resources and Irrigation’s latest data up to mid-September. The Sikta Project has invited four tenders worth […]

  2. Sikta Irrigation Project reports 51 percent progress, data collections of beneficiaries underway

    Ranjha (Banke), Nov 1: The under-construction Sikta Irrigation, a national pride project, has started collecting farmers...

  3. Sikta Irrigation Project collects data on beneficiary farmers

    BANKE: The Sikta Irrigation Project, a national pride project currently under construction, has started collecting data on beneficiary farmers in its command area to ensure effective water distribution and management. The project is collecting data on farmers who are currently receiving irrigation services through branches and sub-branches of the Eastern and Western Main Canals, as […]

  4. Sikta Irrigation Project reaches 51 per cent progress, collects data on water users

    Ranjha (Banke), November 1 The Sikta Irrigation Project, a national pride project under construction in Banke, has begun collecting data on farmers who use its irrigation system to improve water management and ensure services reach the intended beneficiaries. Project Director Raju Acharya said the project was preparing a list of farmers currently receiving irrigation services […] The post Sikta Irrigation Project reaches 51 per cent progress, collects data on water users appeared first on OnlineKhabar English News.